Abbey School – Reading

The project involved the complete relocation of the existing school distribution system to facilitate the construction of a new building.

Working directly with the school and their consultants, we arranged with the local supply authority to divert their existing supplies.

The existing cubical main switch was then dismantled and relocated in a new building.

New sub mains cables were installed and the entire school was re-energised.

Through careful planning and preparation the project was completed within 4 days.

Value approx £40,000